Construction Update

October 2025

Tower 1 :-


Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 50% complete
Tile work: 45% complete
Marble Flooring: 70% complete
Door Frames: 80% complete
PoP work: 70% complete
HVAC work: 50% complete

Tower 2 :-


Structure work Complete.
Plumbing Internal: 95% complete
Plumbing External: 75% complete
Fire Fighting: 80% complete
Tile work: 60% complete
Marble Flooring: 80% complete
Door Frames: 95% complete
PoP work: 80% complete
HVAC work: 75% complete

Tower 3 :-


Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 90% complete
Fire Fighting: Complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: 90% complete

Tower 4 :

Structure work at 12th floor in progress.


Tower 5 :

Structure work Complete, Finishing work started.

Tower 6 :-


Structure work Complete.
Plumbing Internal: 40% complete
Plumbing External: 20% complete
Fire Fighting: 45% complete
Tile work: 40% complete
Marble Flooring: 60% complete
Door Frames: 25% complete
PoP work: 60% complete
HVAC work: 25% complete

Tower 7 :

Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 40% complete
Fire Fighting: 10% complete
Tile work: 20% complete
Marble Flooring: 35% complete
Door Frames: 25% complete
PoP work: 50% complete
HVAC work: 15% complete

Tower 8 :   Structure work at 9th floor in progress.
Tower 9 :   Structure work at 4th floor in progress.

Tower 10 :   Structure work at Upper Ground floor in progress.