Tower 1 :-
Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 50% complete
Tile work: 45% complete
Marble Flooring: 70% complete
Door Frames: 80% complete
PoP work: 70% complete
HVAC work: 50% complete
Tower 2 :-
Structure work Complete.
Plumbing Internal: 95% complete
Plumbing External: 75% complete
Fire Fighting: 80% complete
Tile work: 60% complete
Marble Flooring: 80% complete
Door Frames: 95% complete
PoP work: 80% complete
HVAC work: 75% complete
Tower 3 :-
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 90% complete
Fire Fighting: Complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: 90% complete
Tower 4 :
Structure work at 12th floor in progress.
Tower 5 :
Structure work Complete, Finishing work started.