Construction Update

June 2025

Tower 1 :-


Structure work at 39th floor in progress.
Plumbing Internal: 55% complete
Plumbing External: 50% complete
Fire Fighting: 20% complete
Tile work: 40% complete
Marble Flooring: 15% complete
Door Frames: 30% complete
PoP work: 30% complete
HVAC work: 30% complete

Tower 2 :-


Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 40% complete
Tile work: 20% complete
Marble Flooring: 35% complete
Door Frames: 60% complete
PoP work: 50% complete
HVAC work: 35% complete

Tower 3 :-


Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 40% complete
Tile work: 20% complete
Marble Flooring: 35% complete
Door Frames: 60% complete
PoP work: 50% complete
HVAC work: 35% complete

Tower 4 :

Structure work at 5th floor in progress.


Tower 5 :

Structure work at 36th floor in progress.

Tower 6 :-


Structure work Complete.
Plumbing Internal: 20% complete
Plumbing External: Started
Fire Fighting: 20% complete
Tile work: 10% complete
Marble Flooring: 20% complete
Door Frames: Started
PoP work: 40% complete
HVAC work: 15% complete

Tower 7 :

Structure work Complete.
Plumbing Internal: 30% complete
Plumbing External: 10% complete
Fire Fighting: Started
Tile work: Started
Marble Flooring: 10% complete
Door Frames: Started
PoP work: 40% complete
HVAC work: 10% complete

Tower 8 :   Structure work at 3rd floor in progress.

Tower 9 :

Structure work at 1st floor in progress.


Tower 10 :

Structure work at Basement-1 in progress.