Tower 1 :-
Structure work at 39th floor in progress.
Plumbing Internal: 55% complete
Plumbing External: 50% complete
Fire Fighting: 20% complete
Tile work: 40% complete
Marble Flooring: 15% complete
Door Frames: 30% complete
PoP work: 30% complete
HVAC work: 30% complete
Tower 2 :-
Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 40% complete
Tile work: 20% complete
Marble Flooring: 35% complete
Door Frames: 60% complete
PoP work: 50% complete
HVAC work: 35% complete
Tower 3 :-
Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 40% complete
Tile work: 20% complete
Marble Flooring: 35% complete
Door Frames: 60% complete
PoP work: 50% complete
HVAC work: 35% complete
Tower 4 :
Structure work at 5th floor in progress.
Tower 5 :
Structure work at 36th floor in progress.